Wind turbines
Type: VENSYS 82
Capacity: 1.5 MW
Hub height: 85 m
Rotor diameter: 82 m
Average annual electricity production: 46,000 MWh/a
Companies involved in the realisation
Project development & operational management: Wincono Cyprus Ltd.
Wind turbine manufacturer: VENSYS Energy AG
Installation / Erection: Baju Energy GmbH
Transportation & Cranes: T.L.M. Anipsotiki Ltd.
Infrastructur / Civil works: Elite Constructions Ltd.
Subcontractor foundations: WKA Montage GmbH
Electrical works: YTM Stavrides Ltd.
Substation Alstom: Grid Hellas AE
Electrical design: ABE Kunze GmbH
Supervising Engineer Civil Works: Costas Meletiou Consultants
Supervising Engineer Electrical Works: Eliofotou & Zinieris (Meltec)